![]() ![]() ![]()
|
|||
|
|
|||
|
|
|
|
|
|||||||||||||||
|
1. |
ANAO recommends that Defence and DMO set suitable threshold criteria for determining changes in scope to acquisition projects and promulgate advice to staff to allow decision-makers to be provided with sufficient, consistent and appropriate information and advice on potential scope changes.
Defence response: Agreed |
|
2. |
ANAO recommends that Defence develop clear policy guidance on the circumstances in which prepayments will be considered for inclusion in future major acquisition contracts, and maintain an appropriate record of the basis for agreeing to advance payments as part of contract negotiations.
Defence response: Agreed |
|
3. |
ANAO recommends that Defence ensure that liquidated damages arrangements in future major acquisition contracts apply to clearly identified, key contract milestones.
Defence response: Agreed |
3.15 The Committee held a public hearing on Monday 15 June 2009, with the following witnesses:
n Australian National Audit Office (ANAO);
n Defence Materiel Organisation (DMO); and
n Department of Defence (Defence).
3.16 The Committee took evidence on the following issues:
n scope changes;
n capability of the M113;
n timely delivery of the project; and
n value for money.
3.17 The Committee noted there were inconsistencies in what constituted a scope change, asking Defence and DMO for more information. DMO replied that existing policy had been examined, and a review had been conducted. DMO reported that the Defence Procurement Policy Manual (DPPM) was the primary reference document for procurement, and that it complied with Commonwealth legislation and policy as well as internal Defence guidelines. The DPPM addressed the issue of scope changes:
Where the proposed contract amendment will increase the value of the contract, Proposal Approval must also be exercised for the additional amount.[8]
3.18 DMO also noted that there were specified financial thresholds for the approval of changes to capital acquisition projects via DMO instructions.[9]
3.19 The Committee asked whether it was as simple as applying a ratio that would not be proceeded past. DMO replied:
There are a number of delegations and a number of checks and balances that we go through in determining the scope. It involves both Defence and DMO – that is, Defence delivering the project in accordance with the requirements of Defence represented by capability development in this case. Our responsibility is to look at that change in scope – whether it is within the comprehension of the contract and government approval and certainly look at the value and magnitude of it. It is not just a financial consideration; it is about whether it breaches or is comprehended by the intent and the actual government approval. So there are processes there for us to review that, have a look at it and then bring it to government if we feel it needs government approval.[10]
3.20 The Committee asked what had been done to ensure decision makers were provided with sufficient, consistent and appropriate information and advice on potential scope changes. DMO replied that there was a clear process in place in the documentation, and that ‘administrative discipline’ was required to ensure those processes were followed.[11]
3.21 The Committee is pleased to see that the agencies have accepted ANAO Recommendation No. 1, and that DMO believes appropriate processes are in place to inform decision makers on potential scope changes. However, the Committee is somewhat concerned that staff may be unaware of the processes currently in place for providing advice on potential scope changes, and recommends:
Recommendation 6 |
|
|
|
That the Defence Material Organisation (DMO) provide a brief report to the Joint Committee of Public Accounts and Audit (JCPAA) within six months of the tabling of the Committee’s report on the steps taken to ensure DMO staff adhere to the existing processes to inform decision makers of scope changes. |
3.22 The Committee inquired into the capabilities of the upgraded M113, noting that the vehicles were not currently suited to operating in Afghanistan.
3.23 Defence replied that the M113s provided a capability in various types of terrain and environments, and while they were suited to the terrain of Afghanistan, they were not suitable to operate in the current threat environment. Defence reported that the best combat vehicle for the current threat environment in Afghanistan was the ASLAV, and the best general duties vehicle was the Bushmaster. Defence noted that the M113 could be deployed to Afghanistan, but that it would require additional protection due to the current threat environment.[12]
3.24 The Committee asked whether there was an identified need to upgrade the M113s to deal with rocket propelled grenades (RPGs) and Improvised Explosive Devices (IEDs), two key elements of the threat environment in Afghanistan.
3.25 Defence replied that this was the focus of the contract, and that they were also testing passive protection measures used overseas, as well as developing their own passive protection measures independently.[13] Further, Defence noted that the M113s would ‘probably not’ be deployed in a place where there is sustained close combat expected on a daily basis.[14]
3.26 The Committee asked about the likelihood of the M113 upgrade being completed by its deadline. DMO replied that the project had been running a year late for several years, but that it was anticipated that the project would still be completed a year late. DMO noted, however, that the completion of the project by that deadline was still assessed as being ‘high risk’, but that there were incentives in place to encourage the company to complete the project by December 2010, still one year late.[15]
3.27 The Committee is concerned that the delivery of the M113 upgrades may yet be delayed further, and recommends:
Recommendation 7 |
|
|
|
That the Department of Defence and the Defence Materiel Organisation (DMO) provide the Joint Committee of Public Accounts and Audit (JCPAA) with a brief report detailing the progress of the M113 upgrade process, and the likelihood of the project being completed by the revised target date of December 2010. |
3.28 The Committee expressed its concern about the value for money obtained through the upgrade. It asked Defence whether, during the time the upgrade was being considered, any thought had been given to buying new vehicles, rather than upgrading the M113.
3.29 Defence replied that the terms of reference for the review into the business case for the M113 upgrade included a review of further alternatives, including the acquisition of a new vehicle. Defence rejected the purchase of the US Bradley, or similar vehicle, on several grounds:
Vehicles such as the US Bradley are prohibitively expensive. The need for a tracked capability (for mobility reasons in close combat in difficult terrain) was also restated by capability staff as the reason for rejecting replacement of the M113 fleet with a wheeled vehicle (and new wheeled vehicles such as ASLAV are also more expensive than an upgraded M113).
This assessment remains current. To use the Bradley example, the vehicle carries half the troops in comparison to the M113, and therefore Defence would need to buy twice the number of vehicles. Secondly, the Bradley costs four times the M113 upgrade cost and thirdly, the Bradley is 30 tonne and cannot be deployed by C130 (C17s are not suitable for the small dirt strips in our region).[16]
3.30 The Committee noted that a lot of money was being spent on the M113 for little return, comparing it to the Super Seasprite, a Defence procurement project that has been shelved. DMO replied that the Army considered the M113s to be capable assets that are useful, and that the Army would need within the next ten to twenty years due to conditions in Northern Australia and other tropical areas.[17]
3.31 The Committee believes more must be done within DMO to ensure its staff are aware of their responsibilities to report potential scope changes to key decision makers, and believes the implementation of its recommendation would be of benefit.
3.32 The Committee is concerned that the prospect of the M113 upgrade project’s timely delivery is still assessed as ‘high risk’, and is extremely interested in ensuring the project is completed in a timely manner, and wishes to remain informed about the progress of the project.
3.33 The Committee is encouraged to see that alternatives to the M113 upgrade were considered, and that both operational requirements and value for money were primary considerations of Defence and DMO.
3.34 The Committee acknowledges that the M113 is not currently considered to be able to be deployed in Afghanistan due to its unsuitability to the current threat environment, and expresses its hope that it will be able to be readily deployed to other more suitable environments if it is required.
3.35 On a related matter, the Defence Major Projects Report initiated with the JCPAA’s support in 2008 is an important initiative which will give the Parliament an improved capacity to track the progress of major projects such as the M113 project while they are still in train, rather than relying on the scrutiny of individual projects after projects have been completed.
3.36 Further, the Committee has also decided to continue to scrutinise Defence major capital equipment projects, resolving to review ANAO Audit Report No. 48 2008-09 Planning and Approval of Defence Major Capital Equipment Projects which examined the strengthened “two-pass” process for major capital equipment projects implemented following the Kinnaird review as the first post-Kinnaird review audit.